WIP, WIP or WIP?

WIP, WIP or WIP?

When a curious Realtrac user visits the Costs tab for a Job, they may notice that we offer 3 different methods to calculate the WIP for that specific Job. What's the difference? Why would you use one over another? This article will explain the 3 methods and how they differ. (And if you want the short version, Realtrac would recommend leaving using the "Normal" WIP calculation, unless you're certain another WIP algorithm is appropriate for your job.)

WIP Normal Calculation:
Our normal WIP calculation considers how many pieces are complete (*), and assigns a portion of the Total Costs of the Job across the remaining pieces that are not yet complete. (IE: Whether a part is shipping and/or invoiced is irrelevant to the WIP calculation.)

Total Cost of the Job * WIP Factor
WIP Factor is 100% - (Quantity Complete / Quantity to Manufacture).

Example. Job currently has Total Costs (Labor + Buyouts) of $1000.
Job currently has 6 pieces complete with a Quantity to Manufacture of 10.
Our WIP Factor is (100% - 60%) == 40% (In other words, 60% of the job is "done", and the cost for those 6 pieces is now recognized either in Inventory or on the Invoice the user shipped the parts out on.)
Ergo our WIP is $1000 * 40% == $400. Approximately $400 worth of costs (money from the owners pocket) is still on the Shop Floor.

* - A part is considered complete when the user marks the piece as good on the Sigma router operation (typically done via a Shop Floor or Piece Count Panel client). At that point Realtrac makes an entry in the users Realtrac inventory to note that the piece is complete on the job. The Quantity Complete for a Job is shown on the bottom of the Job Order Entry screen.

WIP "Override":
In this mode, we examine the router operations to determine which OP has counted the most number of good pieces. We then subtract out the number of units that have been shipped to determine a rough approximation of how many units are currently being worked on on the shop floor. We then multiply out the number of units on the floor by the estimated cost the user inputs in the Override portion of the Cost tab for the Job.

Example. We have a Job that has 3 different router Operations. As it sits right now OP 10 has marked 15 units complete, OP 20 has marked 14 units complete and OP 30 has marked 10 units complete. Realtrac would examine these 3 OPs and use the 15 units for the calculation.

This job has shipped 10 units, so Realtrac would do the math of (15 pieces complete at OP 10 - 10 units shipped) == 5 units still being worked on on the shop floor. We would then multiply the 5 units out times the unit cost the user input and that would be the WIP for the Job. If the user input a unit cost of $60, the WIP would be 5 units * $60 == $300.

Estimated Cost:
This method may be of use for users that are running long term jobs (generally thousands of parts being delivered over months or years). The user will also have to have a strong handle on the per unit cost of the parts.

The formula is: (Total Job Costs) - ( Estimated Per Unit Cost * Quantity Shipped to Date )

Example. Our job has $100,000 in Total Costs currently. We have shipped 36,000 units so far. The user selects the Estimated Cost option in the Cost tab for the Job, and inputs their estimated cost of $2.50 per unit. The WIP for this job would be $100,000 - (36,000 * $2.50) == $10,000 in WIP.